Friday, June 10, 5000 finalist traveled to "The Mission Olympic School Final"  A real Olympic opening and closing ceremony of the event took place in the Olympic Stadium Amsterdam.

Neo was consulted for the lifting structure of the videoscreen, and developed special suspension beams for the scaffolding of the stage.

Thanks to the innovative design of the lifting construction the structure was quick to install and the strict safety requirements could be met without the use of extra counter weight.

In addition, Neo installed four chain hoist for sponsor expressions above the grandstand using rope access.

Advisory report with drawings of proposed solution
Design contructional parts with 3D CAD
Calculation of parts with use of FEA
Test build in the workshop
Installed hoisting construction
Hoist construction in use
A successful event!